Economic & Environment
1.
Characteristics of Wind Power
Comparing
with the conventional power plant and hydropower station,
wind power is greatly flexible which can be constructed
in a decentralized or centralized way with the capacity
variously from hundreds kW to thousands kW due to its
small single capacity. Another characteristics are because
the funds are comparatively easy to be financed with
the short construction period, merely requiring a year
span from awarding of the purchasing contract to running
which are to be great advantage of turnover and repaying
of fund at an early date.
In
the past 20 years, wind power has advanced rapidly in
technologies, with high content of hi-tech and increased
reliability of sets. Technologies for single capacity
below 1000 kW have been mature. The 1500 kW generator
sets have started its commercialization. Although the
current production cost for wind power is still higher,
it will still continue to be declined along with the
increment of production quantity and technical improvement.
The
wind power is be of prominent advantage in environment-friendly,
without any toxic gases and waste emissions, and no
requirement of immigration. Although wind power field
covers a large amount of lands, the actual utilization
areas are comparatively small for the foundation of
wind generator and road, not affecting on the normal
production of agricultural fields and pastoral farm.
The places with versatile winds are usually belonging
to the desolate sands or mountains. The construction
of wind power field takes full use of the land, but
develop the travel resources as well.
Due
to the random variation of wind velocity, the unstable
performance of wind power may lead to a certain degree
of undulation. If the capacity of wind power were 10%
lower than that of the grid, no any obvious effects
would be occurred. So far the pumped storage power station
has been built within many grids to adjust the peak,
making this problem in wind power overcome and the wind
resources fully utilized.
2.
Economical Efficiency of Wind Power
1).
Electric Quantity and Electric Price for Grid-Connected
Wind Power
The
annual generation quantity of generator mainly depends
upon the on-site wind resources condition. General speaking,
regarding the generation sets from 200 to 600 kW, under
the condition that the annual average wind velocity
is 7m/s, its annual utilization hours can reach 2400
to 2800 hours, that is the capacity co-efficient of
27% to 32%. The available rate, that is the percentage
that trouble-free times cover the whole year times,
can reach 95% to 98%. For example, wind power field
with the capacity of 10,000 kW, it can provide about
25 million kWh electricity to connect to the grid.
The
former electricity department has once appeared publicly
the regulations on wind power grid connection, with
which core content was that the grid management department
should allow the wind power field connect to the nearby
grid and should purchase the total electric quantity
connected to the grid; the electric price for grid-connected
wind power field should be defined under the principle
of generation cost plus repayment capital with interest
and reasonable profits, taking account of bearing capacity
of consumer, and the value-added tariff should be collected
in addition to the electric price. For those parts that
are higher than the average electric price of the grid,
the balance should be shared equally by the total grid,
and will be purchased by the electricity company.
This
regulation theoretically reflected the social effects
of wind power, its input bearing by the society. In
actual practice, due to the fact that the electric quantity
of wind power takes up a comparatively small percentage
in the grid, the increased burden towards the consumer
is very little; as a result the operability is thus
available. This regulation had intentions to cultivate
the wind power market, to make the client that invested
on the wind power field developed in a sustainable way,
to drive the initiation of local large-scale wind generator
manufacturing, and to promote the scientific research
on wind energy technologies. But the incentives prices
on wind power still depended upon the importance attached
by the provincial leaders and finally approved by the
provincial price bureau.
2).
Current Wind Power Cost and Calculations on Electric
Price During Repayment Period in China
If
it is calculated in accordance with the wind power installed
capacity for per kW, supposing the situation that the
main engines are imported with the C.I.F price of 7000
Yuan/kW, and local-made tower framework, medium-sized
wind field, and annual utilization of 2500 hours, then
the annual generation quantity will be 2500 kWh, and
20 years of service life and 1 year of construction
period. Due to the short construction period for wind
power, if still in accordance with the electric quantity
of 2000kWh, the total generation quantity for 21 years
will be 52000 kWh. If the total project investment were
11000 Yuan/kW, and the annual operation expenses were
calculated in light of 5% of the total investment, then
the electric price of grid connection after the repayment
can be equal to the highest electric price of power
plant (0.48 Yuan/kWh, 1996).
Under
the limit condition that the financial earning rate
in the total investment will not be lower than 12%,
the financial earning rate in the capital in cash will
not be lower than 15%, and the repayment method is temporarily
defined to repay according to the capability; the first
circumstance is to estimate the cost of wind power,
not taking account of interest and taxes, under the
condition that 80% are no-interest load, 20% are own
fund and the repayment period is 10 years:
a.
the average total production expenses in utilization
period: 0.43Yuan/kWh
b.
the electric price for grid connection during
the repayment period: 0. 84Yuan/kWh
c.
the financial earning rate for the total investment:
12.2%
d.
the financial earning rate for the capital in
cash: 41.3%.
The
second situation is to strike for favorable policy with
lower interest and lower taxes. The discount interest
load covers 80%, the annual rate is 6%, repayment period
is 10 years and the own funds takes up 20%. The import
taxes and value-added tax derived from importing are
totally 5%. 12 years depreciation, no requirement of
collecting the income tax during the repayment period,
and 33% of income tax to be collected after the repayment
period, no value-added taxes.
a.
the average total production expenses in utilization
period: 0.51Yuan/kWh
b.
the electric price for grid connection during
the repayment period: 0. 91Yuan/kWh
c.
the financial earning rate for the total investment:
12.5%
d.
the financial earning rate for the capital in
cash: 24.7%.
From
the above calculations, it is showed that the average
total production expenses during the utilization period
for wind power are approaching to that of newly invested
hydropower and thermal power plant. However, in order
to repay the load, the electric price remains greatly
higher than that of conventional power plants during
the repayment period. Thanks to the sound social effects,
it is still required the government support and incentives
policy.
|